Hello,
We are in the middle of an upgrade cycle to move to BW 7.31 Level 5. The upgrade has been done in our DEV and QA. I made a
small change (adding one DTP) to a process chain in DEV. I sent the transport to QA. In our previous version (7.01 Level 9), when you went to the target system ( QA for example) after transporting a process chain, and you double clicked the process chain, the Modified version had to be explicitly activated in the target system for it to become the Active version.
After transporting the slightly altered process chain from DEV to QA, I went into QA and double clicked the process chain. I saw that the Active
version already included the new DTP. Great. Apparently in 7.31 you no longer have to activate a process chain after a transport. However, I also discovered that the process chain executed as soon as the Method Execution (0) Successfully Completed entry was in the transport log. That’s not good. This particular chain is a Local chain that is called from another process chain. It is not a Periodic job and is set to Immediate start. To be absolutely sure of this behavior, I later needed one more DTP in the process chain. I added the DTP in DEV and transported the process chain to QA. When I saw the transport complete, I logged in to QA, went to RSA1, and did a Manage on a cube I knew would be loaded by the process chain. Sure enough there was a new load request running. I never even went into RSPC, so I know I did not execute the process chain. Have any of you experienced this behavior? If so, is there an OSS Note that corrects this issue? I did a Notes Search but couldn’t find anything.
Thanks in advance,
Ben Fitzgerald
Senior Engineer
NIIT Media Technologies, LLC
Augusta, GA